Sh48bn new pipeline is 90% complete – KPC - The Star, Kenya

Cabinet Secretary Ministry of Energy and Petroleum Charles Keter with Energy Permanent Secretary Eng. Joseph Njoroge and Petroleum Permanent Secretary Andrew Kamau listen to Julius Ouma, maintenance Engineer as he explains the fueling process ...

Oil pipeline works to be done by next April - K24 TV

Oil marketers are set to enjoy lower costs from April next year when the Sh48 billion pipeline upgrade is expected to be completed. Kenya Pipeline Corporation Managing Director Joe Sang says the overall project completion is at 68 per cent while ...

KPC says new oil pipeline to be launched next April - Business Daily (press release) (blog)

Kenya Pipeline Company (KPC) has pledged to launch the new oil pipeline by next April to ease the flow of petroleum products in the country. SHARE THIS STORY. Tweet. 0 inShare. Managing director Joe Sang said construction of the Sh48 billion ...